NJ Natural Gas Main Replacement Project
NJ Natural Gas Main Replacement Project
Complete Main replaced, all services up to the house replaced. Meters replaced depending on age.:
Affected Streets:
**Old Squan Road
**Willow Way
**Spruce Ave.
**Cherry Place
Schedule:
**4/4 Door Hanger Notices
**4/10 NJNG AutoDialer to residents with details
**4/17 (week of) Testholes
**4/24 Gas Main Installation Begins - 200' per day - 12 days
**5/8 (week of) Services replaced - 2 to 3 weeks
**Mid-July - After temporary patch settlement, completion of paving.
Paving Plan:
NJNG will use the latest technology to accomplish these line replacements which are expected to only disturb individual portions of one side of the pavement on 3 of the 4 streets. Their plan is to then fully pave the affected half side of each street. If both sides need to be disturbed, full curb to curb will be paved.
***Cherry Place may require pavement-disturbance on both sides if they have to move the main from one side of the street to the other. If so, they will pave curb-to- curb.