Euclid Ave./Watson Place/Holly Place Roadway Improvements

Improvements to the area of the eastern end of Euclid Avenue between South Potter Avenue and Perrine Boulevard and including Watson Place and Holly Place.  The improvements include roadway improvements, pedestrian and handicap accessibility improvements, crosswalk upgrades and drainage improvements. 

Funding:

During the summer of 2019  Borough engaged in a highly competitive process to qualify for very limited 2020 Federal Community Development Block Grant funds via a program administered by Monmouth County.  In September, 2020 the Borough was advised it had received the second highest award in the County, $160,000, to apply toward this project.

Tentative Schedule:

April, 2020 – Official notice of the award will issue via the federal government.

August, 2020 – The funds will be made available

Fall/Winter, 2020, final design, bidding, award

Spring, 2021, construction

Project Contact:

Thomas F. Flarity, Borough Administrator